SELECTION SUMMARY
도입 판단 요약
Building permit application processing times (https://www.winnipeg.ca/building-development/building-renovating/permit-processing-times/buildingpermits) for reviews show the average number of business days to notify of a decision on an application. Metrics are updated monthly to reflect data from the previous month. Definitions: - Part 9 applies to all buildings three storeys or less in building height with a building area not exceeding 600 m2, and with major occupancies classified as Group C, D, E, F-2 or F-3. Part 3 applies to all other buildings.